Current MMS Detailed Fabrication Schedule (03 Dec. 1996 version) 
					rev. 20-Jan-1997
					rev. 18-Feb-1997
  

  Ass. of lowerplate                             12/27 (completed)
  Ass. of backplate                             - 1/30 (completed)
  dimension inspection                          - 1/31 (completed)
  Ass. of lower lampshade panel(4)              - 2/13 (completed)
  Ass. of piston core                           - 2/14 (completed)
  Ass. of coils                                 - 2/17
  Ass. of lower lampshade panel(3,3M)           - 2/18
  Ass. of donuts                                - 2/18
  Ass. of lead, piping                          - 2/19
  Ass. of teacup                                - 2/20
  Ass. of upper lampshade panel                 - 2/20
  Overall test, Inspection                      - 2/24
o Witness                                  2/26 - 2/28
  Desass. and packing                      2/28 - 3/ 7
  Shipping from Melco Kobe works                  3/ 8
  Custom clearance etc.                         - 3/19
  Depart from Kobe port                           3/20 (fixed)
  Arrival at New york port                        4/21