General schedule in the last half of FY2014
Experiments using DALI2 are scheduled in the last half of FY2014 by using 238U and 48Ca primary beams.
Machine time schedule related to DALI2
238U beam
Oct. 23 - Oct. 27
- NP1012-RIBF61 by T. Aumann (with CRYPTA + LaBr3)
Oct. 27 - Oct. 29
- NP1306-RIBF51R1 by O. Wieland (with LaBr3)
48Ca beam
Nov. 17 - Nov. 25
- NP1312-RIBF56R1 by H. Baba (with CRYPTA + LaBr3)
Nov. 26 - Dec. 2
- NP1312-SAMURAI16R1 by A. Corsi and Y. Kubota (with MINOS)
Dec. 5 - Dec. 10
- NP1312-RIBF03R1 by P. Fallon - CANCELED -
General schedule in the first half of FY2014
Several experiments using DALI2 are scheduled in the first half of FY2014 by using 238U primary beam.
Machine time schedule related to DALI2
Apr. 3 - Apr. 6
- NP1306-RIBF31R1 by H. Wang and N. Aoi
Apr. 6 - Apr. 9
- NP1306-RIBF98R1 by A. Jungclaus and P. Doornenbal - CANCELED -
Apr. 30 - May. 10
- NP1312-RIBF118 by P. Doornenbal and A. Obertelli: SEASTAR collaboration